Easton Companies was selected as the Civil Contractor for the 5th and Main Offsite Improvements project. Located in the heart of downtown Bozeman, the project required constant communication with the City of Bozeman, adjacent businesses and the general public for closures and shutdowns. This project included removing and replacing the existing sewer main and services, asphalt milling and paving and setting new manholes, to deliver service to a new commercial project.
- Remove and replace 1,271 linear feet of live 8″ sewer main
- Remove and replace 815 linear feet of live 4″ sewer main
- 34 SS services
- Mill and overlay of existing streets
- Reconstruction of 1/2 block of existing roadway
Location: Bozeman, MT
Project Size: Forthcoming
Market: Civil
Services Provided:
- Water main and services
- Sewer main and services
- Asphalt milling
- Paving
- Curb and gutter